RCECloud
Resource summary
Name | Start Date | End Date | Duration | % Complete | Assignment Cost |
---|---|---|---|---|---|
Evan | 4/25/16, 8:15 AM | 8/1/17, 5:00 PM | 195w 4d 0.25h | 63% | |
Brad | 7/29/16, 4:30 PM | 8/3/16, 4:30 PM | 3d | 100% | |
Sarah | 8/1/16, 8:00 AM | 3/8/17, 5:00 PM | 3w 3d | 72% | |
Bill | 0h |
Earned Value Analysis Summary
Planned Value | Earned Value | Actual Cost | Cost Variance | Schedule Variance | Estimate at Completion | Budgeted at Completion | Variance at Completion | CPI | SPI | CV % | SV % | TCPI |
---|---|---|---|---|---|---|---|---|---|---|---|---|